Planning Committee Meeting: 3311 Greenbank Road

The Official Plan and Zoning for 3311 Greenbank Road will be considered by the City of Ottawa Planning Committee on Tuesday, March 27, 2018.

The Planning Committee meeting will begin at 9:30 a.m. in the Champlain Room, City Hall, 110 Laurier Avenue West, Ottawa. You are welcome to attend the meeting and present your views.

Attached is a copy of the report outlining the Departmental recommendations, including a copy of the proposed Official Plan Amendment.

The Planning Committee will consider any written submissions in respect to this matter if provided to the Committee Co-ordinator of the Planning Committee at 110 Laurier Avenue West, Ottawa, K1P 1J1 or by fax at 613-580-9609 or by e-mail at Melody.Duffenais@ottawa.ca.

If you wish to speak to the Committee please call the Committee Coordinator, Melody Duffenais at 613-580-2424, extension 20113 in advance of the meeting and preferably, by at least 4:30 p.m. on the day before the meeting.

If you wish to listen to this meeting via audiocast on Ottawa.ca, you may do so by accessing the URL below when the meeting is underway: http://app05.ottawa.ca/sirepub/agendaminutes/index_en.aspx

(more…)

Update: Extension of Half Moon Bay Road to Greenbank Road

An update from Jan Harder.

Here is a brief construction update on the extension of Half Moon Bay Road to Greenbank Road:

  1. The underground works have been completed.
  2. City staff expect the asphalt to be placed by the end of next week (Oct 26th), pending weather.
  3. The City is responsible for the asphalt line painting and traffic control signs.  The appropriate City Department is aware of this project and have estimated that this work can occur within 4 weeks after asphalt (by Nov 23rd).
  4. There are a few street lights that need to be installed.  The design has been approved by the City and it's expected the formal approval letter to allow the installation from the City next week.
  5. It's anticipated the street lights will be installed by November 23rd.
  6. Once the street lights are installed it typically takes Hydro Ottawa two-weeks to activate them.
  7. It is staff's opinion that the city does not open the road until the street lights have been activated and the traffic control signs and painting are in place for safety.
  8. Based on the above schedule it's anticipated the road will be complete to be opened by December 7th.
  9. The City's Street Light Department and Hydro Ottawa will be engaged to see if the Street Light activation can be advanced further.